Re: Calculation Price per unit of Electricity

#177
From: John
Date: Tue, 10 Apr 2007 13:20
48 lines
2965 bytes
Please can you send me the equation that you used.

Thanks
"Bruno Campanini" <BC@gmail.com> wrote in message
news:4617d5ca$0$17946$4fafbaef@reader1.news.tin.it...
> <John@eskom.co.za> wrote in message
> news:ev2gui$3n$1@newsreader02.ops.uunet.co.za...
> > Supose a complany develops a new power plant. The construction cost is
100
> > million $ payable on the 1 January 2008. The current maintenance cost s
> > are
> > 8 million $ per annum plus 2 million $ per 1 million units of
electricity
> > consumed. Assume the quantity of Electrical produced is the same as the
> > quantity consumed. The consumption is 1 million units per annum
beiinning
> > in
> > 2008.
> >
> > Company X borrows the full amount for the construction cost as well as
the
> > the other expenses exceeding the income at a rare of intrest of 5 %per
> > annum. The debt is paid with the income exceeding the expenditure.
Assume
> > all annual costs and income are paid at the end of the year. Ignore any
> > taxes.
> >
> > Calculate the price per unit of Electricity to enable company X to break
> > even over a term of 50 years starting on the 1 of January 2008, assuming
> > the
> > power plant is worthless after 50 years.
>
> Figures are in million $.
> You need 5.48 i.e. (100 * 0.05) / (1 - 1 / (1 + 0.05)^50)
> per annum for paying back 100.
> Then you need 10 every year (8 + 2) for maintenance.
> 5.48 + 10 = 15.48 are due at the end of each year, starting
> Dec. 31, 2008.
> Then you must sell your 1 million units of electricity at 15.48
>
> It is not clear to me what "Company X borrows the full
> amount for the construction cost as well as the
> the other expenses exceeding the income..." really means.
> First income (15.48) occurs with first payments (5.48 + 8 + 2)
> i.e. Dec. 31, 2008 and the two amounts are the same...
>
> Bruno
>
Technical Details
Message-ID: <evg2uk$u4g$1@newsreader02.ops.uunet.co.za>
Path: arc1-ca.pugleaf.net!g2news1.google.com!news3.google.com!out04b.usenetserver.com!news.usenetserver.com!in01.usenetserver.com!news.usenetserver.com!news.tele.dk!news.tele.dk!small.news.tele.dk!lnewsinpeer00.lnd.ops.eu.uu.net!bnewsinpeer00.bru.ops.eu.uu.net!emea.uu.net!uunet.co.za!newsreader02.ops.uunet.co.za!newsreader02.ops.uunet.co.za!not-for-mail
References: <ev2gui$3n$1@newsreader02.ops.uunet.co.za> <4617d5ca$0$17946$4fafbaef@reader1.news.tin.it>

Show Full Headers
Complete Article Headers
X-Google-Thread: 10d67e,a37d1a4bbf4db367
X-Google-Attributes: gid10d67e,public
X-Google-Language: ENGLISH,ASCII-7-bit
Path: arc1-ca.pugleaf.net!g2news1.google.com!news3.google.com!out04b.usenetserver.com!news.usenetserver.com!in01.usenetserver.com!news.usenetserver.com!news.tele.dk!news.tele.dk!small.news.tele.dk!lnewsinpeer00.lnd.ops.eu.uu.net!bnewsinpeer00.bru.ops.eu.uu.net!emea.uu.net!uunet.co.za!newsreader02.ops.uunet.co.za!newsreader02.ops.uunet.co.za!not-for-mail
From: John@eskom.co.za
Newsgroups: aus.mathematics
Subject: Re: Calculation Price per unit of Electricity
Date: Tue, 10 Apr 2007 15:20:08 +0200
Organization: UUNET SA
Lines: 50
Message-ID: <evg2uk$u4g$1@newsreader02.ops.uunet.co.za>
References: <ev2gui$3n$1@newsreader02.ops.uunet.co.za> <4617d5ca$0$17946$4fafbaef@reader1.news.tin.it>
X-Trace: newsreader02.ops.uunet.co.za 1176211221 30864 147.110.52.59 (10 Apr 2007 13:20:21 GMT)
X-Complaints-To: abuse@uunet.co.za
X-Priority: 3
X-MSMail-Priority: Normal
X-Newsreader: Microsoft Outlook Express 6.00.2800.1437
X-MimeOLE: Produced By Microsoft MimeOLE V6.00.2800.1441