Last Monday, October 15, the Fairfax County Board of Supervisors approved the VDOT-recommended design for widening Stringfellow Rd in which different types of bicyclists are accommodated on-road with dual 14-foot wide curb lanes and off-road with a 10-ft wide asphalt sidepath. While the space allotted for on-road bicycling is less than ideal, and VDOT's (lowered) 40 MPH roadway design speed is still too fast, this decision is another landmark in recognizing the validity of on-road bicycle travel in Northern Virginia. Below is a local newspaper report, followed by the Clerk's report of the Board of Supervisor's action. Please THANK the Fairfax County Board of Supervisors [ http://www.fairfaxcounty.gov/government/board/ ] for supporting on- road bicycling accommodation in this County-funded highway project, especially in the face of strong opposition from some neighborhood associations. Kudos to everyone who helped make this happen! The performance of "the bicycle lobby" was awesome. Allen Muchnick, president Virginia Bicycling Federation PO Box 5621, Arlington VA 22205-5621 vbf@vabike.org 703-271-0895 http://vabike.org ==== [ http://www.connectionnewspapers.com/article.asp? article=89113&paper=62&cat=104 ] Design OK'd for Stringfellow Supervisors approve amended design to widen road. By Bonnie Hobbs October 18, 2007 The Fairfax County Board of Supervisors on Monday endorsed VDOT's design plan to widen Stringfellow Road. And although it didn't turn out completely the way local residents wanted it, the amendments adopted solve two of their three major concerns. THE SECTION of Stringfellow from Fair Lakes Boulevard to Route 50 is being widened from two lanes to four between Route 50 in Chantilly and Route 29 in Clifton/Centreville. Stringfellow's long been designated a four-lane, divided road on the county's Comprehensive Plan. A 2004 bond referendum provided $16 million for design and right-of-way acquisition, and November's transportation bond could bring the $21 million more needed to construct it. VDOT's proposing two inner travel lanes, 12-feet-wide each; two outer travel lanes, 14-feet wide each; a 10-foot multipurpose trail; a 6- foot sidewalk; and a raised, 16-foot, grass median. But in July, nearly 100 members of Chantilly's Poplar Tree Estates community voiced their objections to VDOT. They didn't like the idea of bicyclists traveling alongside vehicles in the 14-foot lanes, and they said the design was so wide that it encroached on their property and endangered their children's safety. And they and school-system officials said the median would prevent left turns into or out of Rocky Run Middle School, and northbound school buses would have to enter via Poplar Tree Road. VDOT would still like only buses permitted to enter Rocky Run from Stringfellow, but Poplar Tree Estates Homeowners Association President Steve Smith said that would force parents to cut through his community to reach the school. And Supervisor Michael R. Frey (R-Sully) sided with him and the parents. "I MADE CLEAR [to VDOT] that our support was contingent upon full access for everybody, not just buses," said Frey. "That's outstanding," said Smith. VDOT's currently considering two options for it: * Move the entrance farther south, further away from the Poplar Tree intersection. But the existing pipeline may not allow that, so VDOT's asking its Richmond headquarters for permission to: * Obtain a waiver of the minimum distance permitted between left-turn crossovers (between the school and Poplar Tree Road). And, said Frey, "If for some reason, neither of these options can be done, VDOT will have to come back to us again." Originally, the design would have consumed portions of several yards on the Poplar Tree Estates side of Stringfellow. But 1 1/2 weeks ago, Frey, VDOT and the residents met informally and hammered out some changes. They reduced the road's speed from 45 to 40 mph, thereby enabling VDOT to design tighter curves that need less room. VDOT also agreed to move the above-ground electric line and utility poles on the Greenbriar side of the road back a bit. That area was already open space and, said Frey, VDOT discovered that moving those poles wasn't as cost-prohibitive as it had feared. "By shifting them toward Greenbriar, VDOT was able to shift the whole roadbed east without taking anyone's property in either Greenbriar or Poplar Tree," explained Frey. And, said Smith, "I'm extremely pleased with that." But he wasn't at all happy that the bike lanes remained as part of the two, 14-foot travel lanes. "What disturbs me is that the road continues to be too wide because of the on-road, bike lanes," said Smith. "They're bike lanes to nowhere." Because of them, he said, "The road is wider to cross, so it poses a danger to our children." At the end of the July meeting, Frey had said he wouldn't approve those lanes. So on this issue, said Smith, "He misled our community; Michael caved to the bicycle lobby." "IN MY OPINION, the safety of our children is jeopardized by having to cross an extra four feet of road," continued Smith. "I'm terribly disappointed." However, countered Frey, "When you add all the stuff you have to cross--the travel lanes, median, sidewalk and path, curb and gutter-- the four-foot difference is a tiny percentage of the entire road width. They're putting clearly delineated crosswalks at every intersection, plus countdown signals [for pedestrians]. And if people get caught in the middle of the road, he said, "They'll have a median--a four-foot island for safe harbor--until the light changes. So I think they've made the road as safe as possible where you have pedestrians mixing with vehicles." Regarding the on-road bike lanes, Frey said, "It's a changing society. [I believe] we're not there, yet, in terms of the demand for [them]. But through the design of highways, we help that along" for the future. Throughout this whole process, said Frey, "My first priority was, and still is, protecting the homeowners--and we were able to eliminate the physical impacts on the rear yards of the Poplar Tree residents along Stringfellow. And if it came down to an either/or, I would have sided with the homeowners. But since VDOT was able to move the road, it was a win-win for everyone." © 2003 Connection Newspapers. All Rights Reserved. ==== Official summary of October 15, 2007 Fairfax County Board of Supervisors action, from pages 20-21 at [ http://www.fairfaxcounty.gov/bosclerk/summary/2007/07-10-15.pdf ] : 24. A-8--ENDORSEMENT OF DESIGN PLANS TO WIDEN STRINGFELLOW ROAD (ROUTE 645) FROM ROUTE 50 TO FAIR LAKES BOULEVARD (ROUTE 7735) (SULLY AND SPRINGFIELD DISTRICTS) (11:48 a.m.) Supervisor Frey moved that the Board concur in the recommendation of staff and endorse the Virginia Department of Transportation's design plans, as presented at the June 12, 2007, public hearing, to widen Stringfellow Road (Route 645) from Route 50 to Fair Lakes Boulevard (Route 7735) to four lanes including two 12-foot inside travel lanes and two 14-foot wide curb lanes for on-road bicycle accommodations with curb and gutter, a raised median, a 6-foot sidewalk on the west side, and a 10-foot shared use path on the east side, with the following modifications: * Shift the road alignment to the east to minimize the impact of the road widening on adjacent residential properties, and to better utilize existing right-of-way on the east side of Stringfellow Road. Continue to coordinate with the Poplar Tree Homeowners Association and others to reduce property impacts. Balance property impacts on both sides of the road with respect to utility relocation. * Consider options to provide full access for school buses to Rocky Run Intermediate School from Stringfellow Road, and continue coordination of this issue with the school administration and Rocky Run Intermediate School Parent-Teachers' Association (PTA) members. * Incorporate an interparcel service road to consolidate access to Greenbriar Park and the Greenbriar Community Center as requested by the Park Authority. * Continue coordination with the Public Library regarding signalized access to Chantilly Library. * Evaluate options to minimize impacts to the existing stormwater management ponds on Poplar Tree Park and Chantilly Park properties and consider low impact design practices in reconstructing the existing ponds. * Extend project limits to include dual left turn lanes from westbound Fair Lakes Boulevard to southbound Stringfellow Road. * Consider landscaping to minimize the visual impact of the road widening on adjacent property owners. * Reduce the design speed and use a higher (barrier) curb design to reduce impacts and improve safety. With reference to bulleted item number two, Supervisor Frey amended the motion that Board approval is contingent upon providing full access to the school and if the design exception is not approved and the second option of moving it to further south cannot be achieved, that the issue will return to the Board for decision and resolution. Supervisor McConnell seconded the motion. Following discussion regarding the bicycle lanes, the question was called on the motion, as amended, and it carried by unanimous vote. ====
Technical Details
Message-ID:
<1193031962.845587.253180@v29g2000prd.googlegroups.com>Path:
arc1-ca.pugleaf.net!g2news2.google.com!postnews.google.com!v29g2000prd.googlegroups.com!not-for-mailShow Full Headers
Complete Article Headers
X-Google-Thread: 10e8b3,a1c802319adf618b,start X-Google-Attributes: gid10e8b3,public,usenet X-Google-Language: ENGLISH,ASCII Path: arc1-ca.pugleaf.net!g2news2.google.com!postnews.google.com!v29g2000prd.googlegroups.com!not-for-mail From: Allen Muchnick <muchnick@capaccess.org> Newsgroups: dc.biking Subject: Fairfax BoS OKs Stringfellow Rd Wide Curb Lanes! Date: Sun, 21 Oct 2007 22:46:02 -0700 Organization: http://groups.google.com Lines: 210 Message-ID: <1193031962.845587.253180@v29g2000prd.googlegroups.com> NNTP-Posting-Host: 4.249.96.174 Mime-Version: 1.0 Content-Type: text/plain; charset="iso-8859-1" Content-Transfer-Encoding: quoted-printable X-Trace: posting.google.com 1193031963 22681 127.0.0.1 (22 Oct 2007 05:46:03 GMT) X-Complaints-To: groups-abuse@google.com NNTP-Posting-Date: Mon, 22 Oct 2007 05:46:03 +0000 (UTC) User-Agent: G2/1.0 X-HTTP-UserAgent: Mozilla/4.0 (compatible; MSIE 6.0; Windows 98; .NET CLR 1.1.4322),gzip(gfe),gzip(gfe) Complaints-To: groups-abuse@google.com Injection-Info: v29g2000prd.googlegroups.com; posting-host=4.249.96.174; posting-account=ps2QrAMAAAA6_jCuRt2JEIpn5Otqf_w0