REPORTS ADOPTED BY COUNCIL - JULY 13, 1992
PLANNING AND ECONOMIC DEVELOPMENT COMMITTEE
1. 1. That operation of the Facade Loan Program be extended beyond the
existing sunset date of June 30, 1992 for a period of 18 months, at
which time the effectiveness of the program should again be
assessed. The program would offer a 30% forgiveness incentive
until December 31, 1992, after which the impact of this feature
would be evaluated for extension at the same or reduced level.
2. That the proposed Downtown Interior Improvement Assistance Loan
Program as outlined in the staff report dated June 25, 1992 from T.
O'Brien be adopted by the City of Kitchener and offered to eligible
applicants. This program would feature forgiveness incentive rates
and sunset dates identical to the Facade Loan Program.
3. That Schedule 'A' - Facade Improvement Loan Program and Schedule
'A' - Downtown Interior Assistance Loan Program, each be modified
to reflect the following revisions:
- under Funding, paragraph #3, insert a new sentence to read to the
effect that "The Commissioner of Finance and the City Solicitor be
authorized to obtain appropriate financial security to secure the
loan portion of the program".
- under Funding, paragraph #5, be deleted in its entirety
- under Eligibility, paragraph #1, delete the first sentence which
reads "To be eligible for this program, applicants must not be in
default of any municipal taxes, local improvements, utility
accounts, or any other money owing to the City of Kitchener."
(AS AMENDED)
2. 1. That Kitchener Council adopt the Kitchener Office Location Study
dated April 1992 by resolution as an implementation plan and that
the recommendations contained in the study, as listed hereunder, be
used as a basis for the preparation of new city-wide office
location official plan policies:
1.1 That the City of Kitchener's current approach of encouraging new
office development to locate in the Downtown, in part, by
restricting the number of alternative suburban office locations, be
revised to create a more balanced approach that recognizes the
existence of distinct downtown and suburban office sub-markets
within the overall regional office market.
1.2 That the City of Kitchener create new opportunities for locating
freestanding offices in locations outside of Downtown Kitchener.
1.2.1 That the City of Kitchener continue its approach of
permitting freestanding offices to locate in suburban
locations that abut or are near major interchanges of the
Provincial Highway System and Homer Watson Boulevard and
the major interchanges that abut or are near Primary
Arterial roads that provide direct access to the
Provincial Highway System.
1.2.2 That the City of Kitchener permit freestanding offices in
entrance locations to existing areas that are currently
designated as Business Park and remove the existing gross
floor area restrictions that apply to office uses zoned
Business Park Service Centre Zone (B-3).
1.2.3 That the City of Kitchener explore the possibility of
permitting freestanding offices to locate in the Huron
Business Park through the Huron Community Plan Review.
1.2.4 That the City of Kitchener consider freestanding office
uses as one of the primary land uses in a strategy to
help redevelop existing inner city industrial areas,
thereby achieving more effective use of existing serviced
lands and buildings, providing additional inner city
employment opportunities and promoting proximity of place
of residence to place of work.
1.3 That the City of Kitchener continue to recognize that Downtown
Kitchener is, and will remain, an important and unique office
location in the regional office market for offices that require a
prestige location, good overall accessibility to other parts of the
region, and proximity to services and other office functions that
are located within the Downtown. Further, that the Kitchener
Economic Development Department continue to aggressively seek to
attract such new offices to Downtown Kitchener.
1.4 That the office policies/regulations in the Neighbourhood
Commercial, Community Commercial Core, Community Shopping Centre
and Service Commercial Official Plan land use categories and
Comprehensive Zoning By-law 85-1 categories remain unchanged.
1.5 That the Planning and Development Department and the Economic
Development Department be directed to prepare an annual survey of
city-wide trends in office type, location, floor area and
employment and provide a report on the results of each survey to
the Planning and Economic Development Committee.
2. That Kitchener Council direct staff to proceed to prepare the
official plan amendments required to implement the recommendations
that are contained in the Kitchener Office Location Study.
3. That Official Plan Amendments and Zone Change Applications
conforming to the approved office location policies be processed
without the necessity to bring them forward to the Planning and
Economic Development Committee for direction for processing.
3. A. That Official Plan Amendment Application 91/15 (Berkshire Building
Corporation) requesting an amendment to the Kitchener Official Plan
from General Industrial to General Industrial with a special policy
on lands described as Part of Lot 32, Registrar's Compiled Plan
1489, more particulary described as Part 1 of Plan 58R-5097, be
refused.
B. That Zone Change Application 91/38/H/LB (Berkshire Building
Corporation) requesting a change in zoning from General Industrial
(M-2) to General Industrial (M-2) with a special use and a special
regulation provision, all according to By-law 85-1, on lands
described as Part of Lot 32, Registrar's Compiled Plan 1489, more
particularly described as Part 1 of Plan 58R-5097, be refused.
It is the opinion of this Committee that the refusal of these
applications is proper planning for the City.
(DEALT WITH UNDER DELEGATIONS AND CARRIED)
4. A. That Kitchener City Council request the Council of the Regional
Municipality of Waterloo to modify Official Plan Amendment No. 99 -
Victoria Street Secondary Plan in accordance with: 1) the
modifications that are recommended in the Region's post-circulation
letter dated April 30, 1992; 2) the City of Kitchener's revised
standardized wording for inner city secondary plan land use
categories and; 3) to reflect the Region of Waterloo's approval of
Official Plan Amendment No. 127 -City Wide Institutional, such
modifications to include the following:
2.1 SECTION 2 - PURPOSE OF THE AMENDMENT
Revise the second sentence of the first paragraph to read "This
amendment will redesignate...".
2.2 SECTION 3 - BASIS OF THE AMENDMENT
Revise the second sentence of the second paragraph to read "The
Industrial designation covers...
2.3 SECTION 3.1 - TRANSPORTATION POLICY
Revise the third sentence of the second paragraph to read "Similar
removal of this proposed Primary Road designation was previously
undertaken with respect to other affected areas through OPA No. 75
- Victoria Park Secondary Plan and OPA No. 101 - Road Designation
Revisions to Official Plan Maps 1, 2, 3 and 4."
[Poster's note: Anyone actually reading these postings?]
2.4 SECTION 3.2 - LAND USE DESIGNATIONS
Revise sub-section 3.2.7 Major Institutional by deleting the
existing text and replacing it with the following new text:
"It is recognized that the existing Low Density Residential
land use designation is an inappropriate land use designation
to be applied to the Hydro Electric Commission of Kitchener-
Wilmot (H.E.C.K.W.) operations located at 301 Victoria Street
South and some adjacent lands located on the same block
generally bounded by Patricia Avenue, Victoria Street South,
the Grand River Railway, West Avenue and the Henry Sturm
Greenway, given the scale and nature of H.E.C.K.W.'s
operations. The Major Institutional land use designation is
seen as being the most appropriate alternative land use
designation for the subject block; however, a Special Policy
is required to recognize the existence of executive and
administrative offices and associated warehousing and outdoor
storage."
2.5 SECTION 4 - THE AMENDMENT
2.5.1 Revise policy 4.1.1 to read "Public service uses as
defined in Policy VI.IX of this Plan shall be
permitted. . . " .
2.5.2 Revise policy 4.2.1 by deleting the phrase "
shall be replaced by Schedule 'A'..." and replacing
it with the phrase "... shall be amended as shown
on Schedule 'A'...".
2.5.3 Revise policy 4.2.2 by deleting the phrase "
shall be replaced by Schedule 'B'..." and replacing
it with the phrase "... shall be amended as shown
on Schedule 'B'...". Also, replace "Flood Plan"
with "Flood Plain".
2.5.4 Revise policy 4.2.3 by deleting the phrase "
shall be replaced by Schedule 'C'..." and replacing
it with the phrase "... shall be amended as shown
on Schedule 'C'...".
2.5.5 Revise policy 4.2.4 by deleting the phrase "
shall be replaced by Schedule 'D'..." and replacing
it with "...shall be amended as shown on Schedule
'D'...".
2.5.6 Revise policy 4.3.2 such that it makes reference to
"... attached schedule 'A' dated June 9, 1992".
2.5.7 Add new policy 4.3.3 as follows:
"Map 2, 'Flood Plain and Environmental Areas shall
be amended to show the revised floodlines of
Westmount Creek as shown on the attached Schedule
'B' dated June 9, 1992."
2.5.8 Revise the first sentence of Policy 4.4.1 Low
Density Conservation to read:
"Permitted uses are restricted to single detached
dwellings, duplexes, semi-detached dwellings,
conversion of existing housing stock to multiple
dwellings to a maximum of three units, multiple
dwellings to a maximum of three units, small
residential care facilities, home occupations and
private home day care.
2.5.9 Revise the second sentence of the first paragraph
of Policy 4.4.2 Low Rise Multiple Residential to
read:
"Permitted uses are restricted to single detached
dwellings, duplexes, semi-detached dwellings,
conversion of existing housing stock to multiple
dwellings, multiple dwellings, small residential
care facilities, home occupations, and private home
day care.
2.5.10 Revise the second sentence of the first paragraph
of Policy 4.4.3 Low Density Multiple Residential to
read:
"Permitted uses are restricted to single detached
dwellings, duplexes, semi-detached dwellings,
conversion of existing housing stock to multiple
dwellings, multiple dwellings, small residential
care facilities, home occupations and private home
day care."
2.5.11 Revise the first sentence of the first paragraph of
Policy 4.4.4 Medium Density Multiple Residential to
read:
"Permitted uses are restricted to existing single
detached dwellings, duplexes, existing semi-
detached dwellings, multiple dwellings up to a
maximum density of 200 units per hectare (80 units
per acre), day care facilities provided they are
located internal to a multiple dwelling, small and
large residential care facilities, private home day
care and home occupations."
2.5.12 Revise the first two paragraphs of Policy 4.4.5 Low
Density Commercial Residential to read:
"Permitted residential uses are restricted to
single detached dwellings, duplexes, semi-detached
dwellings, the conversion of existing housing stock
to multiple dwellings, lodging houses, home
occupations, private home day care, small and large
residential care facilities and multiple dwellings.
Commercial uses are restricted to office uses
including health offices and health clinics, club
facilities, funeral homes, financial
establishments, religious institutions, medical
laboratories, day care facilities, studios and
personal services. Commercial, residential and
religious institution uses may be located within
separate buildings or may mix within the same
building. Retail uses shall not be permitted.
Personal services must be located within a building
used primarily for other commercial or multiple
residential uses.
New residential development may not exceed a
density of 100 units per hectare (40 upa), within a
Maximum Floor Space Ratio of 1.0, that is, the
above grade building floor area shall not exceed
1.0 times the lot area."
2.5.13 Delete the existing text of Policy 4.4.7 Major
Institutional in its entirety and replace it with
the following new text:
"Permitted uses within the Major Institutional land
use category shall be restricted to hospitals,
health office, health clinics, medical
laboratories, small and large residential care
facilities, educational establishments, religious
institutions, museums, day care facilities,
community centres, studios, sports and/or
recreation facilities, veterinary services, and
social service establishments.
Convenience retail, financial establishment and
personal service uses shall be permitted provided
that they are located within a building used for a
health clinic, multiple dwelling or large
residential care facility.
Multiple residential uses developed in association
with permitted institutional uses may be permitted
to a maximum net residential density of 200 units
per hectare (80 units per acre).
Commercial uses developed in conjunction with, and
intended to directly serve permitted institutional
uses, may be permitted."
2.6 SPECIAL POLICIES
Add new Section 2.6 Special Policies as follows:
"2.6 SPECIAL POLICIES
2.6.1 Notwithstanding the Major Institutional
land use designation which applies to the
lands located on the block generally
bounded by Patricia Avenue, Victoria
Street South, the Grand River Railway,
West Avenue and the Henry Sturm Greenway,
the executive and administrative offices
of the Hydro Electric Commission of
Kitchener-Wilmot located at 301 Victoria
Street South and the associated
warehousing and outdoor storage uses
shall be permitted uses.
4. B. That City of Kitchener Council request the Council of the Regional
Municipality of Waterloo Council to defer approval of the land use
designations proposed for the area shown on Map 1 (attached) to
permit City and Regional staff further opportunity to attempt to
resolve an objection to the residential land use designations in
this area by C.N. Rail.
It is the opinion of this Committee that approval of these
modifications to Official Plan Amendment No. 99 is proper planning
for the City.
5. That Zone Change Application 92/9/M/PMc (Lena Bremner) requesting a
change in zoning from General Residential (R3) and Semi-Restricted
Residential (R2) to Semi-Restricted Residential (R2) with and extension
of use and special regulations according to By-law 4830 on Part of Lot
3, Registered Plan 370, be approved in the form shown in the proposed
By-law attached, dated June 9, 1992, subject to the following conditions
being satisfied prior to any readings of the By-law by Council.
1. To arrange for notification by letter from the Regional
Municipality of Waterloo to the City's Clerk, that all Regional
requirements have been satisfied with respect to the proposed
development.
2. The Owner acknowledges that Condition 1 is required to be satisfied
no later than seven (7) months from Council having approved the
amending zoning by-law relative to the Zone Change Application
92/9/M/PMc by resolution. In the event this requirement is not
fulfilled within the seven month period, Council shall consider
rescinding its zone change approval.
It is the opinion of this Committee that the approval of this
application is proper planning for the City.
6. That the following revisions to City Council's July 17, 1989 conditions
of approval relative to Draft Plan of Subdivision 30T-87063 (Vace Farms
Ltd.) be approved:
That condition 65 be amended by inserting the words "only 15 building
permits shall be issued within the subdivision prior to the
construction of Wabanaki Drive, and further that" no 'additional'
building permits ... after the words performance security
arrangements in the first sentence so that the revised condition 65
shall read as follows:
65. The Subdivider agrees that notwithstanding any other
conditions or performance security arrangements, only 15 building
permits shall be issued within the subdivision prior to the
construction of Wabanaki Drive, and further that no additional
building permits shall be issued for any lots or blocks contained
within this Plan of Subdivision until such time as Wabanaki Drive is
constructed between Wilson Avenue and Hidden Valley Road, to the
satisfaction of the City's Commissioner of Public Works. In this
regard, the Subdivider shall be responsible for the installation of
a two (2) lane road being the Wabanaki Drive Extension from Wilson
Avenue to the new local access road for the Hidden Valley area to
binder asphalt constructed to City of Kitchener standards as approved
by the City's Commissioner of Public Works including gravel shoulders
and adequate storm ditches. Further, the Subdivider shall pay 100%
of the cost and agrees and acknowledges that the City's 60%
responsibility as set out in the Development Charge Policy as
reflected in Section 34. of an Agreement registered on the 7th day of
September 1990 as Instrument Number 1052245 no longer applies.
(DEALT WITH UNDER DELEGATIONS AND CARRIED)
7. A. That Zone Change Application 91/41/M/ZJ (Michael & Ethel Vilandre)
requesting a change in zoning from Agricultural (A) according to
Township of Waterloo By-law 878A to Restricted Residential (R2A)
with special regulations, on Part of Lot 60, German Company Tract,
be approved, in the form shown in the proposed by-law attached,
dated June 1, 1992, subject to the following conditions being
satisfied prior to any readings of the amending zoning by-law by
Council.
1. To arrange for notification by letter from the Regional
Municipality of Waterloo to the City's Clerk, that all
Regional requirements have been satisfied with respect to
the proposed zone change.
2. The Owner acknowledges that Condition 1 hereof is
required to be satisfied no later than seven (7) months
from the date of Council having approved by resolution,
the amending zoning by-law relative to Zone Change
Application 91/41/M/ZJ. In the event this requirement is
not satisfied within the seven month period, Council
shall consider rescinding their zone change approval.
It is the opinion of this Committee that approval of this
application is proper planning for the City and is in conformity
with the City's Approved Official Plan.
7. B. That City Council waive the requirement of a 4.95 metre road
widening along the entire frontage of 9 MacVille Avenue, as
provided for under the City's Official Plan.
8. A. That Zone Change Application 90/15/H/JW (Rockway Holdings Limited)
requesting a change in zoning from Agricultural (A-1) to
Agricultural (A-1) with special use and special regulation
provisions on Lots 10-14 inclusive, 24-26 inclusive and Part Lots
9 and 23, Registered Plan 585 and Part Lot 149, German Company
Tract, be approved in the form shown in the Proposed By-law,
attached, dated June 4, 1992, subject to the following conditions
being satisfied prior to any readings of the By-law by Council:
1. That the owner enter into a Development Agreement to be
prepared by the City Solicitor and registered on title and the
following conditions shall form part of this agreement:
The Owner agrees:
1. To prepare a landscaping plan showing planting and surfacing
details for all areas outside the Limits of Extraction as
shown on Map No. 2 of the Proposed By-law attached to Report
PD 58/92, to obtain approval thereof from the City's Director
of Development prior to any readings of the By-law by Council
and to complete the landscaping in accordance with the
approved plan within one year of commencing the stripping of
topsoil on site.
2. To maintain the approved landscaping in a state acceptable to
the City's Director of Development for the life of the
proposed pit.
3. To prepare a detailed Grading and Drainage Control Plan
showing drainage details for the subject property, abutting
properties and public rights-of-way so as to ensure compatible
drainage, and to show thereon all detailed erosion and
siltation control features; to obtain approval thereof from
the City's Commissioner of Public Works, prior to any readings
of the By-law by Council. The Owner agrees to implement all
erosion and siltation control measures prior to the
commencement of any site grading, to complete the site grading
and drainage scheme in accordance with the approved plan
within one year of commencing the stripping of topsoil on
site, and to maintain the erosion and siltation control
measures for the life of the proposed pit.
4. To close all redundant driveways to the Regional Municipality
of Waterloo's standards prior to commencing the stripping of
topsoil on site.
5. To install, at the Owner's cost and to the Regional
Municipality of Waterloo's standards, new driveway ramps
prior to commencing the stripping of topsoil on site.
6. That, owing to the proximity of nearby dwellings, berm
construction adjacent to Huron Road shall not occur only in
the months of June, July or August.
7. That the haulage route shall not include any portion Trussler
Road south of Ottawa Street unless or until such time as said
portion of Trussler Road is upgraded to Truck Route status.
8. That, wherever possible, extraction shall be carried out at
the elevation of the pit floor.
9. That the operation of any machinery or equipment used in
conjunction with the pit, other than water pumping equipment,
shall not occur between the hours of seven o'clock in the
afternoon (local time) and seven o'clock in the morning (local
time) of the next day or on any Sunday or holiday unless
written permission is obtained from the City's Commissioner of
Public Works for special projects.
10.(i) To provide, prior to commencing the stripping of topsoil
on site, a cost estimate for 100% of the total cost of
all "site development works" required to be done by this
Agreement. Such cost estimate shall include materials,
installations, removals, closures and restorations, other
than within the area of extraction, and shall be in a
form satisfactory to the City's Director of Development.
(ii) "Site Development Works" shall be applicable only outside
of the area of extraction and shall include the
following:
a) On site works:
Rough grading; fine grading; plant material; sodding and
seeding; and
b) Off site works:
Redundant driveways; driveway ramps; fine grading; and
sodding.
(iii) To provide prior to commencing the stripping of topsoil
on site, for each phase, a Letter of Credit to the City's
Director of Development for 50% of the total cost of all
site development works in a form satisfactory to the City
Solicitor, to be held by the City as security for the
completion of the works required in this Agreement. The
Letter of Credit will be retained until such time as 50%
of the value of the site development works
have been completed in conformity with their approved
design. Thereafter reductions shall commence for
additional works completed in conformity with their
approved designs, in amounts in accordance with the cost
estimate, subject to the receipt of verification in
writing from the Owner's consultants that such works are
so completed.
(iv) The Letter of Credit shall be kept in force until the
completion of the required site development works in
conformity with their approved designs. If the Letter of
Credit is about to expire without renewal thereof and the
works have not been completed in conformity with their
approved designs, the City may draw all of the funds so
secured and hold them as security to guarantee completion
unless the City Solicitor is provided with a renewal of
the Letter of Credit forthwith.
(v) In the event that the owner fails to complete, to the
satisfaction of the City's Director of Development, the
required site development works in conformity with their
approved designs within one year of commencing the
stripping of topsoil on site, then it is agreed by the
Owner that the City, its employees, agents or contractors
may enter on the lands and so complete the required site
development works to the extent of monies received under
the Letter of Credit. The cost of completion of such
works shall be deducted from the monies obtained from the
Letter of Credit. In the event that there is a surplus,
the City shall pay it forthwith to the Owner. In the
event that there are required site development works
remaining to be completed, the City may by by-law
exercise its authority under Section 325. of The
Municipal Act to have such works completed and to recover
the expense incurred in doing so in like manner as
municipal taxes.
(vi) Other forms of performance security may be substituted
for Letters of Credit provided that approval is obtained
from the City Treasurer and the City Solicitor.
11. To operate the pit in accordance with all applicable
provincial and municipal requirements. In particular,
the Owner acknowledges the existence of By-law 87-345,
being a By-law to Regulate the Operation of Pits and
Quarries, and agrees to operate the pit in strict
compliance thereto.
12. That the City may give a Release of this Agreement as it
applies to the lands or portions thereof. This Release
shall not, however, release this clause or any of the
conditions related to site works which are required by
this agreement to be maintained for the life of the
proposed pit.
13. To forward a copy of each written report, required
pursuant to Section 17 of the Aggregate Resources Act, to
Kitchener's Department of Planning and Development for
information.
-------
8.A 2. To arrange for notification by letter from the Regional
Municipality of Waterloo to the City's Clerk, that all Regional
requirements have been satisfied with respect to the proposed
development.
3. The owner acknowledges that the registered Development Agreement
required in Condition 1, the approvals or provisions of
conditions 1.1, 1.2 and 1.10.(iii) and Condition 2 hereof are
required to be satisfied no later than seven (7) months from
Council having approved the amending zoning by-law relative to
the Zone Change Application 90/15/H/JW by resolution. In the
event this requirement is not fulfilled within the seven month
period, Council shall consider rescinding its zone change
approval.
It is the opinion of this Committee that the approval of this
application is proper planning for the City and is in conformity with
a recommended Amendment (No. 118) to the City's Approved Official Plan.
8.B That the Ministry of Natural Resources have regard to the
following matters in considering the application of Rockway
Holdings Limited for a Class A Licence on Lots 10-14 inclusive,
24-26 inclusive and Part Lots 9 and 23, Registered Plan 585 and
Part Lot 149, German Company Tract:
1. Approval by the City of Kitchener of a zoning by-law to
permit a pit is based on the Existing Features Plan,
Operational Plan and Notes, and Progressive Rehabilitation
and Final Rehabilitation Plans and Notes, dated 92 04 06 and
attached to Report PD 58/92.
2. The City of Kitchener objects to the inclusion of Note 24 on
the Operational Plan as no application has been made to the
City of Kitchener to permit a portable asphalt plant on the
site.
3. The City of Kitchener requires the owner to enter into a
Development Agreement to be registered on title prior to any
readings of the By-law by Council. The conditions which
shall form part of this agreement are detailed in part (A) of
this resolution.
9. That Staff adopt a more permissive stance with respect to the approval
of condominium conversions under the Rental Housing Protection Act.
That in considering approval of condominium conversions, regard shall
be had to:
1. The overall rental housing vacancy rate in the City of Kitchener;
2. The supply of rental housing in areas where condominium
conversions are Proposed;
3. The impact of a conversion on existing tenants.
10. That a special meeting of the Planning and Economic Development
Committee be held on Monday, July 13, 1992 commencing at 4:00 p.m. to
consider the Region of Waterloo 'Vision Paper to 2021' and the City's
Vision in respect to the Official Plan Review.
11. That Demolition Control Application DC 92/4/RM (Kenmore Commercial
Inc.) requesting approval for the demolition of a single detached
dwelling (farm house) and two framed sheds located at 601 Glasgow Lane,
legally described as Lot 6 and 28 Benjamin Weber's Survey, Registered
Plan 402 be approved subject to the following:
a) That the attached site plan, dated June 26, 1992, be approved in
principle, with the final site plan and the following condition
included in a Development Agreement pursuant to Section 41 of
the Planning Act:
"The Owner agrees to construct and substantially complete the
approved site development not later than two years from the day
demolition of the existing detached dwelling is commenced. Upon
failure to complete the approved site development within two
years, the Clerk of the Municipality shall be entitled to enter
on the Collector's Roll to be collected in like manner as
municipal taxes, the sum of $20,000 for each dwelling unit for
which demolition permits have been issued and such sum shall,
until payment thereof, be a lien or charge upon the land in
respect of which the permit to demolish the residential property
is issued."
It is the opinion of this Committee that approval of this application
is proper planning for the City.
Technical Details
Message-ID:
<Bs5Mw0.Dx7@watdragon.uwaterloo.ca>Path:
arc1-ca.pugleaf.net!sparky!uunet!watmath!watdragon.uwaterloo.ca!watyew!jdnicollShow Full Headers
Complete Article Headers
Newsgroups: kw.general Path: arc1-ca.pugleaf.net!sparky!uunet!watmath!watdragon.uwaterloo.ca!watyew!jdnicoll From: jdnicoll@watyew.uwaterloo.ca (James Davis Nicoll) Subject: July 13 Minutes, Part Two Message-ID: <Bs5Mw0.Dx7@watdragon.uwaterloo.ca> Sender: news@watdragon.uwaterloo.ca (USENET News System) Organization: University of Waterloo Distribution: kw Date: Wed, 29 Jul 1992 14:28:48 GMT Lines: 673