Shuttle Status for 01/20/93 (Forwarded)
Author: Peter Yee
Date: Thu, 21 Jan 1993 21:48
Date: Thu, 21 Jan 1993 21:48
52 lines
2459 bytes
2459 bytes
SPACE SHUTTLE STATUS REPORT
Wednesday, January 20, 1993
George H. Diller
Kennedy Space Center
407/867-2468
Vehicle: OV-102/Columbia
Current location: OPF Bay 2
Mission: STS-55/Spacelab D-2 Inclination: 28.45 degrees
Launch timeframe: February, wk 4 Nominal Landindg Site: KSC
Mission Duration: 8 days 22 hours Crew Size: 7
IN WORK TODAY:
- installation of Spacelab tunnel
- hydraulic test of flight controls
- position flight control elements for rollover
- orbiter/external tank door functional test
- orbiter aft compartment closeouts
- orbiter mid-body closeouts
WORK COMPLETED:
- Spacelab D-2 Interface Verification Test (IVT)
- payload bay cleaning
- ammonia boiler servicing
WORK SCHEDULED:
- payload bay door radiator inspections Saturday
- Crew Equipment Interface Test on Sunday
SPECIAL TOPICS--Endeavour post landing analysis:
OV-105 touched down at 08:38:17 a.m. EST on Tuesday, landing
approximately 1,500 feet from the Runway 33 threshhold about
three feet right of centerline, and rolling out approximately
8,700 feet.
Brake and tire wear was normal, except for a cut 5/16th-inch
deep and two plys of scuffing on the right inboard tire. There
were 57 debris impacts, with 13 greater than one inch. Four to
five tiles are expected to be replaced.
Endeavour arrived at OPF Bay 1 at approximately 2 p.m. Tues-
day where deservicing is now in work.
Thread Navigation
This is a paginated view of messages in the thread with full content displayed inline.
Messages are displayed in chronological order, with the original post highlighted in green.
Use pagination controls to navigate through all messages in large threads.
Back to All Threads