STS-55 SPACE SHUTTLE STATUS REPORT
Monday, January 25, 1993
George H. Diller
Kennedy Space Center
407/867-2468
Vehicle: OV-102/Orbiter Columbia Location: OPF Bay 2
Primary payload: Spacelab D-2 Crew Size: 7
Launch timeframe: NET Feb. 25 10:30 a.m.
Mission duration: 8 Days 22 Hours Nominal Landing Site: KSC
Inclination: 28.45 degrees Initial orbital altitude: 184 sm
STS-55 IN WORK:
- Spacelab final power-up
- payload bay door test cycles
- orbiter aft main engine compartment closeouts
- main propulsion system closeouts
- Ku-band antenna stowage
- thermal protection system tile closeouts
STS-55 WORK COMPLETED:
- Crew Equipment Interface Test (CEIT)
- Spacelab laboratory module closeouts
- Spacelab tunnel Interface Verification Test (IVT)
- Spacelab tunnel leak checks
- avionics bay closeouts
- payload bay door radiator stowage
STS-55 WORK SCHEDULED:
- aft structural leak check
- orbiter composite pressurization test
- weight and center of gravity determination
- install Columbia on orbiter transporter
- roll to the VAB the first week in February
___ _____ ___
/_ /| /____/ \ /_ /| Ron Baalke | baalke@kelvin.jpl.nasa.gov
| | | | __ \ /| | | | Jet Propulsion Lab |
___| | | | |__) |/ | | |__ M/S 525-3684 Telos | Every once in a while,
/___| | | | ___/ | |/__ /| Pasadena, CA 91109 | try pushing your luck.
|_____|/ |_|/ |_____|/ |
Thread Navigation
This is a paginated view of messages in the thread with full content displayed inline.
Messages are displayed in chronological order, with the original post highlighted in green.
Use pagination controls to navigate through all messages in large threads.
Back to All Threads