SPACE SHUTTLE STATUS REPORT
Tuesday, January 26, 1993
George H. Diller
Kennedy Space Center
407/867-2468
Vehicle: OV-102/Orbiter Columbia Location: OPF Bay 2
Primary payload: Spacelab D-2 Crew Size: 7
Launch timeframe: NET Feb. 25 10:30 a.m.
Mission duration: 8 Days 22 Hours Nominal Landing Site: KSC
Inclination: 28.45 degrees Orbital altitude: 184 sm
STS-55 IN WORK:
- crew compartment closeouts/close crew access hatch
- orbiter aft main engine compartment closeouts
- main propulsion system closeouts
- orbiter mid-body closeouts
- thermal protection system tile closeouts
STS-55 WORK COMPLETED:
- payload bay door test cycles
- tire leak check
- Ku-band antenna stowage
- Crew Equipment Interface Test (CEIT)
- Spacelab laboratory module closeouts
- avionics bay closeouts
- payload bay door radiator stowage
STS-55 WORK SCHEDULED:
- aft structural leak check/orbiter composite pressurization test
- weight and center of gravity determination
- install Columbia on orbiter transporter
- close payload bay doors on Saturday
- roll to the VAB on February 2 or 3
___ _____ ___
/_ /| /____/ \ /_ /| Ron Baalke | baalke@kelvin.jpl.nasa.gov
| | | | __ \ /| | | | Jet Propulsion Lab |
___| | | | |__) |/ | | |__ M/S 525-3684 Telos | Every once in a while,
/___| | | | ___/ | |/__ /| Pasadena, CA 91109 | try pushing your luck.
|_____|/ |_|/ |_____|/ |
Thread Navigation
This is a paginated view of messages in the thread with full content displayed inline.
Messages are displayed in chronological order, with the original post highlighted in green.
Use pagination controls to navigate through all messages in large threads.
Back to All Threads