SPACE SHUTTLE STATUS REPORT
Thursday, January 28, 1993
George H. Diller
Kennedy Space Center
407/867-2468
Vehicle: OV-102/Orbiter Columbia Current location: OPF Bay 2
Primary payload: Spacelab D-2 Crew Size: 7
Orbital altitude: 184 sm Inclination: 28.45 degrees
Mission Duration: 8 days 22 hours
Launch timeframe: NET Feb. 25 - 9:38 a.m.
Landing site/timeframe: KSC/March 6 - 07:43 a.m.
STS-55 IN WORK:
- remove BREMSAT GAS canister
- Spacelab module positive pressure leak check
- crew compartment closeouts/close crew access hatch
- main landing gear strut hydraulic fluid level checks
- orbiter aft main engine compartment closeouts
- main propulsion system closeouts
- orbiter mid-body closeouts
- thermal protection system tile closeouts
STS-55 WORK COMPLETED:
- Spacelab D-2 closeouts
STS-55 WORK SCHEDULED:
- install aft flight doors on Friday
- waste containment system electrical verification checks
- aft structural leak check/orbiter composite pressurization test
- close payload bay doors for flight on Sunday
- weight and center of gravity determination
- install Columbia on orbiter transporter
- roll to the VAB February 2
___ _____ ___
/_ /| /____/ \ /_ /| Ron Baalke | baalke@kelvin.jpl.nasa.gov
| | | | __ \ /| | | | Jet Propulsion Lab |
___| | | | |__) |/ | | |__ M/S 525-3684 Telos | Every once in a while,
/___| | | | ___/ | |/__ /| Pasadena, CA 91109 | try pushing your luck.
|_____|/ |_|/ |_____|/ |
Thread Navigation
This is a paginated view of messages in the thread with full content displayed inline.
Messages are displayed in chronological order, with the original post highlighted in green.
Use pagination controls to navigate through all messages in large threads.
Back to All Threads