KSC SHUTTLE STATUS REPORT - FRIDAY, MAY 24, 1991 - 10 AM
STS-40/SPACELAB LIFE SCIENCES 1 - COLUMBIA (OV 102) - PAD 39-B
LAUNCH - JUNE 1
WORK IN PROGRESS:
- Retest of the new multiplexer demultiplexer (MDM) involving the
orbiter and booster hydraulic system.
- Inspections and cleaning of temperature tranducers for instal-
lation in the vehicle.
WORK COMPLETED:
- Installation of plugs instead of temperature transducers in the
main propulsion system liquid hydrogen main engine inlets. Offi-
cials determined that these transducers can be eliminated and
still meet the launch commit criteria and flight rules. An
analysis is continuing to determine if the liquid oxygen tempera-
ture transducers can also be eliminated.
- Connections of the new general purpose computer and of the new
MDM.
WORK SCHEDULED:
- Installation of six propellant temperature probes tomorrow.
- Retest of the new general purpose computer tomorrow.
- Closeouts of the aft compartment begin Sunday.
- Start of launch countdown Tuesday at 5 p.m. at the T-43 hour
mark.
- Launch at 8 a.m. EDT Saturday, June 1. Launch window closes at
10 a.m. EDT.
STS-43/TDRS - ATLANTIS (OV 104) - OPF BAY 2
WORK IN PROGRESS:
- Gimbal test of the orbital maneuvering system engines.
- Thermal protection system operations.
- Potable water servicing.
- Water spray boiler leak and functional tests.
- Main engine and main propulsion system tests.
- Functional tests of the orbital maneuvering system.
- Tests of the forward reaction control system at the Hypergolic
Maintenance Facility.
- Auxiliary power unit lube oil servicing.
WORK COMPLETED:
- Tests of the ultra high frequency communications system.
WORK SCHEDULED:
- External tank door functional test next week.
- Installation of the forward reaction control system next week.
- Tests of the nose wheel steering system next week.
- Anti-skid brake test planned next week.
STS-48/UARS - DISCOVERY (OV 103) - OPF BAY 1
WORK IN PROGRESS:
- Window polishing.
- Preparations to remove the three shuttle main engines.
- Thermal protection system operations.
- Inspections of the orbiter's hydraulic system.
WORK COMPLETED:
- Main engine flight readiness test.
- Flow checks of the main propulsion system helium regulators.
WORK SCHEDULED:
- Removal of the three shuttle main engines next week.
STS-49 - ENDEAVOUR (OV 105) - VAB HIGH BAY 2
WORK IN PROGRESS:
- Purges of the freon coolant loop.
- Installation of platforms in the midbody and aft compartment.
STS-43 SOLID ROCKET BOOSTERS - VAB HIGH BAY 1
WORK IN PROGRESS:
- Mating the right forward assembly.
- Joint closeouts.
WORK SCHEDULED:
- External tank mate to the boosters on June 3.
--
Eric Behr, Illinois State University, Mathematics Department
Internet: ejbehr@rs6000.cmp.ilstu.edu Bitnet: ebehr@ilstu
Technical Details
Message-ID:
<1991May25.023009.4567@rs6000.cmp.ilstu.edu>Path:
arc1-ca.pugleaf.net!utzoo!utgpu!news-server.csri.toronto.edu!cs.utexas.edu!swrinde!zaphod.mps.ohio-state.edu!hobbes.physics.uiowa.edu!news.iastate.edu!ux1.cso.uiuc.edu!rs6000.cmp.ilstu.edu!ejbehrShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!news-server.csri.toronto.edu!cs.utexas.edu!swrinde!zaphod.mps.ohio-state.edu!hobbes.physics.uiowa.edu!news.iastate.edu!ux1.cso.uiuc.edu!rs6000.cmp.ilstu.edu!ejbehr From: ejbehr@rs6000.cmp.ilstu.edu (Eric Behr) Newsgroups: sci.space.shuttle Subject: Shuttle Status Report 5/24/91 Message-ID: <1991May25.023009.4567@rs6000.cmp.ilstu.edu> Date: 25 May 91 02:30:09 GMT Reply-To: ejbehr@rs6000.cmp.ilstu.edu (Eric Behr) Organization: Central Illinois Surfing Club Lines: 88