🚀 go-pugleaf

RetroBBS NetNews Server

Inspired by RockSolid Light RIP Retro Guy

Article View: sci.space.shuttle
Article #3523

KSC status report 6/5/91

#3523
From: Eric Behr
Date: Fri, 07 Jun 1991 02:41
83 lines
3114 bytes
  KSC SHUTTLE STATUS  -  THURSDAY, JUNE 6, 1991  -- 10:00 a.m.
_________________________________________________________________



         STS-40/SLS-1  -  COLUMBIA (OV 102)  -  ON ORBIT


WORK IN PROGRESS:
*  Solid Rocket Booster recovery ships are scheduled to arrive
Port Canaveral today at 11:30 a.m. and at Hanger AF before 3:00
p.m.
*  Engineers report minimal damage to pad 39-B and mobile
launcher platform following launch yesterday. No damage was
reported in the payload changeout room.

WORK COMPLETED:
*  Launch of Columbia on mission STS-40 with the Spacelab Life
Sciences module occurred yesterday, June 5, at 9:24.51 a.m. EDT.

WORK SCHEDULED:
*  Move mobile launcher platform to VAB high bay 3 (Monday)
*  Columbia is currently scheduled to land at Edwards Air Force
Base, Calif. at 1:14 p.m. EDT, Friday, June 14.


        STS-43/TDRS-E  - ATLANTIS (OV 104)  -  OPF Bay 2
                       LAUNCH JULY\AUGUST
WORK IN PROGRESS:
*  Main engine and main propulsion system checks
*  Main engine heat shield installation
*  Thermal protection system tile work
*  Replacement of left OMS engine actuator due to malfunction
during gimbaling test
*  Payload integration verification test
*  Environmental Control and Life Support System servicing
*  Landing gear functional test

WORK COMPLETED:
*  Main landing gear strut hydraulic level check
*  Gaseous nitrogen leak check
*  Installation of OMS heatshield

WORK SCHEDULED:
*  SSME interface leak checks
*  Payload verification tests
*  Crew equipment interface test

CONCERNS: During leak check of MPS, Helium Supply Tank number 4
was found to be source of helium leak in aft compartment.
Replacement of tank may be necessary.

        STS-48/UARS  --  DISCOVERY (OV 103)  -  OPF BAY 1

WORK IN PROGRESS:
*  Auxiliary Power Unit lube oil servicing
*  Water Spray Boiler leak and functional tests
*  Main propulsion system and OMS pod system checks

WORK SCHEDULED:
*  TACAN system checks
*  Main engine controller checkouts


       STS-49  --  ENDEAVOUR (0V 105)  --  VAB High Bay 2

WORK IN PROGRESS:
*  Main propulsion system leak checks
*  Thermal Protection System work
*  Environmental Control Life Support system checks
*  Partial removal of 2 and 4 inch liquid hydrogen lines


 STS-43 EXTERNAL TANK/SOLID ROCKET BOOSTERS  --  VAB High Bay 1

WORK IN PROGRESS:
*  Electrical mates and checkouts
*  Replacement of lower strut firing line cable

-- 
Eric Behr, Illinois State University, Mathematics Department
Internet: ejbehr@rs6000.cmp.ilstu.edu    Bitnet: ebehr@ilstu
Technical Details
Message-ID: <1991Jun07.024111.8843@rs6000.cmp.ilstu.edu>
Path: arc1-ca.pugleaf.net!utzoo!utgpu!news-server.csri.toronto.edu!rpi!think.com!spool.mu.edu!uwm.edu!ux1.cso.uiuc.edu!rs6000.cmp.ilstu.edu!ejbehr

Show Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!news-server.csri.toronto.edu!rpi!think.com!spool.mu.edu!uwm.edu!ux1.cso.uiuc.edu!rs6000.cmp.ilstu.edu!ejbehr
From: ejbehr@rs6000.cmp.ilstu.edu (Eric Behr)
Newsgroups: sci.space.shuttle
Subject: KSC status report 6/5/91
Message-ID: <1991Jun07.024111.8843@rs6000.cmp.ilstu.edu>
Date: 7 Jun 91 02:41:11 GMT
Article-I.D.: rs6000.1991Jun07.024111.8843
Reply-To: ejbehr@rs6000.cmp.ilstu.edu (Eric Behr)
Organization: Central Illinois Surfing Club
Lines: 83