Article View: sci.space.shuttle
Article #5822Shuttle Status for 05/01/89 (Forwarded)
From: Peter E. Yee
Date: Mon, 01 May 1989 16:59
Date: Mon, 01 May 1989 16:59
53 lines
3184 bytes
3184 bytes
KSC SHUTTLE STATUS REPORT - Monday, May 1, 1989
STS-30 - ATLANTIS (OV 104) - PAD 39-B
Work at Launch Pad 39-B has gone exceptionally well in
readying the Shuttle Atlantis for launch. A four-inch liquid
hydrogen recirculation line has been replaced and leak checks of
a seal in the line are underway. Leak checks of the external
tank-to-orbiter are scheduled and new thermal insulation will be
applied to the newly installed line tonight. Closeouts are
scheduled tomorrow.
One liquid hydrogen recirculation pump was replaced in the
aft compartment. Leak checks of the new pump are underway and
electrical checks are planned later today. Closeouts of the pump
and aft compartment are scheduled for later today and tomorrow.
Metal particles found inside the old pump could have been the
cause for the short. The pump circulates liquid hydrogen to the
main engine number one and conditions it prior to start.
STS-30 crew members went back to Houston this weekend to
practice in the shuttle simulator and will return to KSC two days
prior to launch.
Because of the component replacements, the launch will not
take place for several days. A new launch date will not be set
until today at the earliest. Launch is expected to occur the
latter part of the week.
STS-28 - COLUMBIA - (0V 102) - OPF BAY 1
The right orbital maneuvering system pod was transferred
from its maintenance facility to the OPF on Saturday.
Installation is planned this week. The main engines are also
scheduled to be installed this week. The left pod is scheduled to
be transferred to the OPF this weekend. Orbiter systems testing
and thermal protection system activities are continuing with over
300 tile cavities remaining.
STS-33 - DISCOVERY - (OV 103) - OPF BAY 2
Discovery's right orbital maneuvering system pod was taken
to the maintenance facility for work prior to the orbiter's next
mission. Orbiter systems testing is scheduled.
STS-28 SOLID ROCKET BOOSTERS - VAB
The left forward assembly was stacked this weekend,
completing the left booster. Joint closeouts are active. The
right forward center segment, the third of four solid motors, is
in the VAB transfer aisle and scheduled to be stacked tomorrow.
Technical Details
Message-ID:
<24772@ames.arc.nasa.gov>Path:
arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!ncar!ames!trident.arc.nasa.gov!yeeShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!ncar!ames!trident.arc.nasa.gov!yee From: yee@trident.arc.nasa.gov (Peter E. Yee) Newsgroups: sci.space.shuttle Subject: Shuttle Status for 05/01/89 (Forwarded) Message-ID: <24772@ames.arc.nasa.gov> Date: 1 May 89 16:59:28 GMT Sender: usenet@ames.arc.nasa.gov Reply-To: yee@trident.arc.nasa.gov (Peter E. Yee) Organization: NASA Ames Research Center, Moffett Field, CA Lines: 53