KSC SHUTTLE STATUS - WEDNESDAY, JAN. 3, 1990
STS-32 - COLUMBIA (OV-102) - PAD 39-A
Overnight, final ordnance devices were installed aboard the
vehicle, the firing circuits have been tested and the orbital
maneuvering system and reaction control system tanks have been
pressurized for flight.
Now that the pad has been reopened for normal work, tech-
nicians are busy closing out the aft compartment and are
scheduled to have the doors on for flight by Thursday morning.
Batteries to power the avionics on the Syncom satellite will
be charged today.
The launch countdown is scheduled to begin ticking at 4 p.m.
EST Thursday, Jan. 4 at the T minus 43 hour mark. Several addi-
tional hours of hold time have been included in the count to al-
low resolution of any problems associated with the newly refur-
bished launch pad.
STS-32 astronauts will be arriving at KSC at about 4:30 p.m.
Friday to prepare for the 10-day mission. Launch remains
scheduled for 8:06 a.m. EST, the opening of the 58 minute window.
STS-36 - ATLANTIS (OV-104) - OPF BAY 1
Work is continuing to prepare Atlantis for the STS-36 mis-
sion next month. Transfer of the vehicle to the VAB is planned
in about two weeks.
The vehicle was powered up yesterday and the payload bay
doors were opened for final inspections and cleaning. Leak
checks of the crew cabin were successfully completed yesterday.
STS-31 - DISCOVERY (OV-103) - OPF BAY 2
Today, the vehicle will be powered up and the payload bay
doors opened. A minor GSE hydraulic leak during the holidays
wetted connectors associated with power which had to be cleaned
and verified prior to powering up the vehicle. Orbiter systems
testing will be underway today.
STS-31 SOLID ROCKET BOOSTERS - VAB
The left aft center segment was transferred to the VAB yes-
terday and stacking activities are underway.
Technical Details
Message-ID:
<39638@ames.arc.nasa.gov>Path:
arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!tut.cis.ohio-state.edu!snorkelwacker!apple!bionet!ames!trident.arc.nasa.gov!yeeShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!tut.cis.ohio-state.edu!snorkelwacker!apple!bionet!ames!trident.arc.nasa.gov!yee From: yee@trident.arc.nasa.gov (Peter E. Yee) Newsgroups: sci.space.shuttle Subject: Shuttle Status for 01/03/90 (Forwarded) Message-ID: <39638@ames.arc.nasa.gov> Date: 3 Jan 90 18:13:30 GMT Sender: usenet@ames.arc.nasa.gov Reply-To: yee@trident.arc.nasa.gov (Peter E. Yee) Organization: NASA Ames Research Center, Moffett Field, CA Lines: 49