Tuesday November 7, 1989 (as of 9:30 a.m.)
KSC Space Shuttle Processing Status Report
-----------------------------------------------------------------
STS-33 -- Discovery (OV 103) - Pad 39-B
Overnight, the helium signature test was completed
successfully. Though there was a slight misalignment in one of
the pressurized hoses, the problem was quickly corrected and the
test was completed on schedule. Also in process is work to
replenish the liquid oxygen tanks. LOX replenishment is scheduled
for completion today. The Modular Auxiliary Data Systems (MADS)
recorder will be retested today. Heat shield installation on main
engines two and three has been completed. Tomorrow, the Flight
Readiness Test will be performed on the shuttle main engines.
Today, shuttle managers are concluding their meeting at KSC
for the Flight Readiness Review. This meeting is to assess the
STS-33 launch, mission, landing and recovery teams' readiness for
a safe and successful mission. A launch date and launch period is
expected to be announced following the meeting later this
afternoon.
STS-32 -- Columbia (OV 102) - OPF Bay 2
Power on testing on the orbiter Columbia began this morning
in the Orbiter Processing Facility with power up occuring at 7:00
a.m. In addition, the external tank door latch pull test was
completed Monday and the shuttle main engines hot gas leak checks
were finished overnight. Heat shields will be installed on main
engine number two later today. Payload bay closeouts and
inspections are continuing. Work flows are on schedule for the
orbiter to be rolled over to the VAB November 13. Columbia is
scheduled for mission STS-32 on which the SYNCOM satellite will
be deployed and the LDEF satellite now in Earth orbit will be
retrieved and returned to KSC. Launch is scheduled for December
1989 from pad 39-A.
STS-36 -- Atlantis (OV 104) - OPF Bay 1
The orbiter Atlantis is scheduled to be powered up at 11:00
a.m. today. Yesterday, the orbiter's power system was validated
and the RTG systems installed for the deployment of the Galileo
spacecraft will be disconnected later this week. Atlantis is
currently scheduled for mission STS-36, a Department of Defense
dedicated mission to be launched in February 1990.
STS-32 Solid Rocket Boosters/External Tank - VAB
Connections between the external tank and solid rocket
boosters are being completed and testing of the connections are
underway. The orbiter will be mated to the stack following
rollover planned for next week.
Ron Baalke | (818) 541-2341 x260
Jet Propulsion Lab M/S 301-355 | baalke@mars.jpl.nasa.gov
4800 Oak Grove Dr. |
Pasadena, CA 91109 |
Technical Details
Message-ID:
<2098@jato.Jpl.Nasa.Gov>Path:
arc1-ca.pugleaf.net!utzoo!attcan!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!samsung!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalkeShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!attcan!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!samsung!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalke From: baalke@mars.jpl.nasa.gov (Ron Baalke) Newsgroups: sci.space,sci.space.shuttle Subject: KSC Space Shuttle Report (Forwarded) Message-ID: <2098@jato.Jpl.Nasa.Gov> Date: 7 Nov 89 17:25:44 GMT Sender: news@jato.Jpl.Nasa.Gov Reply-To: baalke@mars.jpl.nasa.gov (Ron Baalke) Organization: Jet Propulsion Laboratory, Pasadena, CA. Lines: 62