KSC SPACE SHUTTLE PROCESSING REPORT - THURSDAY, NOV. 9, 1989
STS-33 - DISCOVERY (OV 103) - PAD 39-B
As planned, a flight readiness test of the three main
engines was completed early this morning. Closeouts of the aft
compartment for flight have started along with checks of the
regulators for the forward reaction control system. Installation
of the extravehicular mobility units, or spacesuits, is scheduled
for Friday.
Activities scheduled this weekend include a hot fire of the
solid rocket booster hydraulic power units, final ordnance
operations, pressurizing the orbital maneuvering system and
reaction control system tanks for flight and loading storage
tanks on the launch tower with liquid oxygen and liquid hydrogen
propellants.
Launch of mission STS-33 is scheduled for Monday, Nov. 20
during a four-hour launch period that begins at 6:30 p.m. EST.
STS-36 - ATLANTIS (0V 104) - OPF BAY 1
Sniff checks of the fuel motor valves in the orbital
maneuvering system were completed and checks of the oxidizer
valves are planned today. Heat shields and engine domes are being
removed in preparation for engine removals scheduled for this
weekend and early next week. A functional test of the startracker
is planned today and an inspection of the 17-inch flapper valve
is scheduled.
STS-32 - COLUMBIA (OV 102) - OPF BAY 2
Final cleaning of the payload bay began early this morning
and closure of the doors is planned for later today. Closeouts of
the vehicle for the move to the Vehicle Assembly Building are
underway. The landing gears are being prepared for flight. The
orbiter transporter will be used to transfer the orbiter from the
OPF to the Vehicle Assembly Building at 12:01 a.m. November 16.
STS-32 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
Installation of ordnance devices is planned for Friday.
Connections between the external tank and solid rocket boosters
are continuing. The orbiter is scheduled to be mated next week.
STS-36 SOLID ROCKET BOOSTERS - RPSF
Yesterday, the left aft center segment was transferred to
the VAB and stacking preparations are underway. Next week, the
left forward center segment will be transferred to the VAB and
stacked.
Ron Baalke | baalke@mars.jpl.nasa.gov
Jet Propulsion Lab M/S 301-355 | baalke@jems.jpl.nasa.gov
4800 Oak Grove Dr. |
Pasadena, CA 91109 |
Technical Details
Message-ID:
<2143@jato.Jpl.Nasa.Gov>Path:
arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalkeShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalke From: baalke@mars.jpl.nasa.gov (Ron Baalke) Newsgroups: sci.space,sci.space.shuttle Subject: KSC Space Shuttle Report (Forwarded) Message-ID: <2143@jato.Jpl.Nasa.Gov> Date: 9 Nov 89 19:53:11 GMT Sender: news@jato.Jpl.Nasa.Gov Reply-To: baalke@mars.jpl.nasa.gov (Ron Baalke) Organization: Jet Propulsion Laboratory, Pasadena, CA. Lines: 59