KSC SPACE SHUTTLE PROCESSING REPORT - WEDNESDAY, NOV. 8, 1989
STS-33 - DISCOVERY (OV 103) - PAD 39-B
Today, a flight readiness test of the three main engines is
underway. This test simulates engine start and shutdown
sequences. In addition, the orbital maneuvering system engines
will be gimbaled and the aerosurfaces will be cycled.
Closeouts of the aft compartment for flight will begin
tomorrow and installation of the extravehicular mobility units,
or spacesuits, is scheduled for Friday. Checks of the regulators
for the forward and aft reaction control systems are planned for
tomorrow and Friday.
Launch of mission STS-33 is scheduled for Monday, Nov. 20,
during a four-hour launch period that begins at 6:30 p.m. EST.
STS-36 - ATLANTIS (0V 104) - OPF BAY 1
Sniff checks of the motor valves in the orbital maneuvering
system are planned today. Heat shields and engine domes are being
removed in preparation for engine removals scheduled for this
weekend and early next week.
STS-32 - COLUMBIA (OV 102) - OPF BAY 2
A visual aid for berthing the Long Duration Exposure
Facility is being installed in the payload bay today. Final
cleaning of the payload bay is scheduled to begin today and
closure of the doors is planned for tomorrow. Closeouts of the
vehicle for the move to the Vehicle Assembly Building are
underway. The landing gears are being prepared for flight. The
orbiter transporter will be used to transfer the orbiter from the
OPF to the Vehicle Assembly Building next week.
STS-32 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB
Installation of ordnance devices is planned for Friday.
Connections between the external tank and solid rocket boosters
are continuing. The orbiter is scheduled to be mated next week.
STS-36 SOLID ROCKET BOOSTERS - VAB
Instrumentation on the left aft booster is being calibrated
today. The left aft center segment will be transferred to the VAB
today in preparation for stacking.
Ron Baalke | (818) 541-2341 x260
Jet Propulsion Lab M/S 301-355 | baalke@mars.jpl.nasa.gov
4800 Oak Grove Dr. |
Pasadena, CA 91109 |
Technical Details
Message-ID:
<2118@jato.Jpl.Nasa.Gov>Path:
arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!samsung!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalkeShow Full Headers
Complete Article Headers
Path: arc1-ca.pugleaf.net!utzoo!utgpu!jarvis.csri.toronto.edu!mailrus!cs.utexas.edu!samsung!usc!henry.jpl.nasa.gov!elroy.jpl.nasa.gov!jato!mars.jpl.nasa.gov!baalke From: baalke@mars.jpl.nasa.gov (Ron Baalke) Newsgroups: sci.space,sci.space.shuttle Subject: KSC Space Shuttle Report (Forwarded) Message-ID: <2118@jato.Jpl.Nasa.Gov> Date: 8 Nov 89 19:57:44 GMT Sender: news@jato.Jpl.Nasa.Gov Reply-To: baalke@mars.jpl.nasa.gov (Ron Baalke) Organization: Jet Propulsion Laboratory, Pasadena, CA. Lines: 54